PFC2017-0462 ATTACHMENT 1 Community Flood Mitigation Measures Program Projects and Timelines     Program   Project  GLENMORE GATES  FLOOD MITIGATION BARRIERS  Centre St Bridge: flood barrier  Heritage Dr SE: flood barrier  West Eau Claire: flood barrier  Bonnybrook Wastewater  Treatment Plant (WWTP): flood  barrier  Sunnyside: flood and groundwater  protection  Downtown: flood protection   Bowness: flood protection   Pearce Estates‐Inglewood: flood  protection   Deerfoot Trail: flood protection1  STORMWATER SYSTEM  IMPROVEMENTS  Sunnyside Pumpstation 1  Sunnyside Pumpstation 2  Upper Plateau Separation  Stormwater outfall improvements  (15 locations)  Bonnybrook WWTP: outfalls and  utility relocation  BRIDGE IMPROVEMENTS  12 St SE  9 Ave SE  GRAVEL BAR (GB) RESHAPING AND  BANK STABILIZATION  Western Headworks Diversion: site  improvements  Flood Recovery Erosion Control       Program     Centre Street Bridge Bow River GB  Scollen Bridge: Elbow River GB  10 Street NW bridge:   Bow River  GB  Mission island:  Elbow River  GB  Crowchild Trail NW:   Bow River   GB  Carburn Park:   Bow River  GB  Inglewood:  Bow River  GB  Prince’s Island:  Bow River  GB  PFC2017-0462 ATT 1 ISC: UNRESTRICTED   Total Cost  ($000’s)  Funded and  Underway1    To be Funded  and  Implemented  Completion  Timeline  $10,000  $97,950  ‐  ‐  ‐  $10,000  $28,550        ‐  $69,400  ‐  ‐  ‐  2020    2018  2018  2019  ‐    ‐  2022  ‐  ‐    2023  ‐  ‐  ‐  ‐      2022  2025  ‐  ‐    2025  ‐  ‐    TBD  $64,500  $19,600  $44,900    ‐  ‐  ‐      ‐        2018  2018  2022  ‐    ‐  2018  ‐    ‐  2022  $44,000  ‐  ‐  $19,000    ‐  $25,000  ‐      2017  2019  $77,410  $54,100  $23,310    ‐  ‐    2017  ‐    ‐  2017  ‐  ‐  ‐  ‐      2018  2020  ‐  ‐    2020  ‐    ‐  2020  ‐  ‐    2021  ‐  ‐  ‐  ‐  ‐  ‐        2023  2023  2025    Community Flood Mitigation Measures Program Projects and Timelines Continued     Program   Project  SANITARY SYSTEM IMPROVEMENTS  Roxboro Sanitary Liftstation  Sunnyside Sanitary Liftstation  PROPERTY LEVEL FLOOD MITIGATION  PROGRAM  OTHER CIVIC PROJECTS  Municipal Complex: drainage  improvements  Zoo: flood mitigation  TOTAL  Total Cost  ($000’s)  Funded and  Underway    To be Funded  and  Implemented  Completion  Timeline  $6,780  ‐  ‐  $6,780      ‐  ‐  ‐    2018  2018  $20,000  ‐  $20,000  TBD  $31,400  $31,400  ‐    ‐    ‐  2016  ‐  $352,040    $169,430  ‐  $182,610  2018    1 Included in The City’s 2014 ACRP application but denied funding as the barrier provides mitigation on  Nose Creek and does not influence mitigation levels for Elbow or Bow Rivers.  TBD – To be determined. PFC2017-0462 ATT 1 ISC: UNRESTRICTED           PFC2017-0462 ATT 1 ISC: UNRESTRICTED      Structtural Comm munity Flood Mitigattion Estimaated Timlin nes    Page 3 of 3 PFC2017-0462 ATT 1 P ISC: UNRESTRICTED D   [Typee a quote from th he document or the summary of  an interesting point. YYou can position the text box  where in the docu ument. Use the Teext Box Tools  anyw tab to o change the form matting of the pu ull quote text  box.]